Omokoroa Town Centre Earthworks

Omokoroa Town Centre Earthworks
Omokoroa
Client: JACE Group

Constructed in the early 1980’s this kiwifruit orchard contained unsuitable material in a filled gully. The first task required was to remove the unsuitable material and replace it with the required engineered fill.

Prior to filling the gully a new 5,000m3 drainage blanket was constructed. The drainage blanket had subsoil drains installed into the base to maintain spring flows. A large clean water lined diversion channel was constructed to capture upstream flows and the excavation area was also the dirty water diversion channel.

The gully was bunded at the base with a 6-inch pump. This was installed with a well head that pumped to the Sediment Retention Pond for treatment daily and as necessary during rain events. Working around the constantly flowing dirty water diversion was achieved by re-shaping cut-off drains, overland pumping, de-watering timing and strategic filling operations.

The project had a cut volume of 30,000m3 and fill volume of 115,000m3 leaving a balance of imported fill required of 85,000m3. SABRE is in their second earthworks season on this project.

SCOPE OF WORKS:

GET IN TOUCH

EXPLORE

DESIGN, SHAPE
& DELIVER WITH US
PLAN, DESIGN
& BUILD WITH US
PROTECT, GROW
& ADD VALUE WITH US

This website uses cookies to ensure you get the best experience on our website.